Request permission from RW-UK to use.

SCCC Cwmbran – this is a Healthcare Project specifically a Specialist and Critical Care Centre in South Wales.

Lot of products on this one, primarily façade switched to RW for non combustibility – some RCS and RockFon products and a lot of RW Fire Protection products.

The project

The Grange University Hospital is a new £350m hospital in Cwmbran, Wales. This state-of-the-art facility forms part of a wider strategic plan which will see Aneurin Bevan Health Board significantly modernise its health service provision.

Originally known as the Specialist Critical Care Centre, the 471-bed facility will bring together more than 40 complex and more acute services onto one site and serve over 600,000 people per year.

As a major healthcare project, main contractor Laing O'Rourke commissioned Central Roofing South Wales Ltd to design and install the roofing and cladding systems – with ROCKWOOL® providing the ideal solution to meet the architect's non-combustible specification.

The site is expected to be operational in November 2020, much earlier than a previously announced date of 2021. This is due to construction programmes being accelerated to ensure the facility could be partially opened as a Nightingale (COVID-19) Hospital, if needed.

Project Location

Grange University Hospital

Llanyravon
Cwmbran
NP44 2XJ
United Kingdom

Once we got the green light we had to move fast. ROCKWOOL was instrumental in helping us to revise the designs at short notice, providing robust technical calculations that gave us confidence in product performance. The fact that we could deliver a non-combustible façade solution with such a small increase in footprint, was a real achievement.

Tony Davies

United Kingdom
Managing Director | Central Roofing South Wales Ltd

The challenge

Plans for the Grange University Hospital were finally given the go ahead in October 2016, with Central Roofing South Wales Ltd working to a façade design which specified PIR insulation on the external of the steel frame structure.

By the time construction started in July 2017, the architect upgraded the specification to non-combustible insulation. This left Central Roofing South Wales Ltd with the challenge of updating the design while minimising impact on the building footprint.

In addition to fire protection considerations, the building design also demanded that a U-value of 0.18W/m²K be achieved in the through-wall construction.

The use of non-combustible insulation was also a key requirement for areas of the flat roof, particularly in critical areas above compartment walls. Central Roofing South Wales Ltd highlighted that non-combustible insulation was needed to insulate the metal deck profiles. This was to provide effective protection in the event a fire started inside the building.

As the architect upgraded the insulation specification to be noncombustible, the design had to be updated while minimising impact on the building footprint.

1/8

The solution

Having partnered with ROCKWOOL on previous projects, Central Roofing South Wales Ltd knew that stone wool insulation is rated non-combustible and felt confident in the company's ability to meet the high volumes of insulation which would be required for the specialist site.

Moreover, as the design had to be changed to stone wool insulation and the package revised in a matter of weeks, Central Roofing South Wales Ltd was confident that ROCKWOOL could provide the necessary technical partnership via U-value calculations and supporting the system design.

Working in partnership with ROCKWOOL, Central Roofing South Wales Ltd revised the façade insulation design to incorporate ROCKWOOL RainScreen Duo Slab®, a dual-density and BBA-certified stone wool insulation product which delivers acoustic, thermal, and fire performance all in one solution.

Once installed, the robust outer surface of the slabs, in combination with a factory applied water repelling agent, acts to resist rain ingress during construction.

Over the duration of the 18-month site programme, Central Roofing South Wales Ltd installed 9,840m² of ROCKWOOL RainScreen Duo Slab, completing the through-wall build-up with a series of non-combustible exterior rainscreen cladding finishes.

On the flat roof 3,930m² of liquid membrane system was installed, with ROCKWOOL HardRock® Multi-Fix Dual Density laid above the metal deck areas to ensure regulation compliance.

For the firestopping, approximately 25,000 penetration seals were installed throughtout the scheme using 3rd party certified products from the ROCKWOOL FirePro® Range.

Watch the case study video below.

Request permission from RW-UK to use.

SCCC Cwmbran – this is a Healthcare Project specifically a Specialist and Critical Care Centre in South Wales.

Lot of products on this one, primarily façade switched to RW for non combustibility – some RCS and RockFon products and a lot of RW Fire Protection products.

The ROCKWOOL Firestopping Solution

For the firestopping, approximately 25,000 penetration seals were installed throughout the scheme using certified products from the ROCKWOOL FIREPRO® Range.

ROCKWOOL Firestopping Range

Article History

Our experts continually review and update our articles when legislation changes or new information becomes available. 

Current version: 3 - 1/08/23

Version 2 - 25/10/20

First published: 07/10/20

More ROCKWOOL Case Studies...